question @ Rane/Serato guys..
Ok, so the first wave of the '57' is a bit behind the 'projected' dates... will the second wave be delayed as well?? or can we expect those in June? Meaning, will the delay affect the next wave?
At 1:22 AM 14 April 2006
click wrote
No. Subsequent runs generally aren't delayed unless a vendor really screws up and sends or builds us the completely wrong thing.
It's the initial buy and "starting the parts supply pipeline" that's really the time consuming and most problematic issue. In fact, while there's a backlog of pre-orders now, once we hit the 2nd or 3rd run, we should be able to make pretty quick work of getting the backlog caught up.
It's the initial buy and "starting the parts supply pipeline" that's really the time consuming and most problematic issue. In fact, while there's a backlog of pre-orders now, once we hit the 2nd or 3rd run, we should be able to make pretty quick work of getting the backlog caught up.
At 3:25 AM 15 April 2006